Skip to Content

We’re live! Explore our new website →

ADA Transition Plan

About the Project

In accordance with Title II of the Americans with Disabilities Act (ADA) and 28 CFR 35.105, local agencies are required to develop and maintain an ADA Transition Plan. The Adams County Board of County Commissioners has approved the ADA Transition Plan to improve access compliance to pedestrian facilities within the county’s jurisdiction.

ADA Transition Plan

Please click here to request the ADA Transition Plan for Public Right-of-Way in Unincorporated Adams County. Transition plan information can be made available in alternative accessible formats upon request. For information about obtaining an alternative format, please use the contacts listed below.

What’s Happening

As part of the Adams County ADA Transition Plan, the county intends to regularly obtain public input to assist the county in developing its potential standalone ADA projects within the public right-of-way. The county generally obtains public input from YourGOV, public meetings, and town hall sessions as well as public contact with the ADA Coordinator.

Contact Us at 720.523.6875 or publicworks@adamscountyco.gov.

Project Overview

Americans with Disabilities Act improvements (curb, gutter, and sidewalks) in the following areas:

  • Area 1: E. 68th Ave. – Washington St. to York St.
  • Area 2: E. 66th Ave. – Washington St. to York St.
  • Area 3: Steele St. – Niver Creek Tr. to E. 86th Ave.
  • Area 4: E. 56th Ave. – Lincoln St. to Washington St.
  • Area 5: E. 55th Ave. – Lincoln St. to Washington St.

Project Cost:

  • Areas 1-4: $5,360,000
  • Area 5: $680,000

Project Schedule

  • Areas 1, 2, 4
  • Engineering Design: Complete
    • Area 3
  • Engineering Design: Mid 2021
    • Areas 1 – 4
  • ROW Acquisition: 2021

Construction Schedule

One area per year 2021, 2022, 2023, or 2024

  • Area 5: Complete

Contact Information

Call 720.523.6875
Email

Map highlighting ADA Five Areas Project locations on major avenues in red.